The wind farm is being developed on a Build-Own-Operate (BOO) basis under a 25-year Power Purchase Agreement with the Egyptian Electricity Transmission Company (EETC), signed in March 2026. EETC’s obligations are backed by Egypt’s Ministry of Finance. The land is made available by the New and Renewable Energy Authority (NREA) under a 25-year usufruct agreement.
Construction started in June 2026, and financial close allows it to proceed at full scale. The wind farm will be connected to the grid in three phases. The first 300 MW phase is expected to enter commissioning in January 2028, and full commercial operation of the 900 MW is planned for the third quarter of 2028. Orascom Construction is carrying out the civil and electrical works for the balance of plant. Goldwind is responsible for the supply, installation and commissioning of the wind turbines.
Non-recourse project financing is provided by the Japan Bank for International Cooperation (JBIC), Proparco, FMO, Société Générale, Crédit Agricole Corporate and Investment Bank and KfW IPEX-Bank. The financing provided by the commercial lenders is covered by Nippon Export and Investment Insurance (NEXI). HSBC Bank Egypt acts as working capital facility bank and onshore security agent.
Once operational, the wind farm is expected to generate approximately 4 TWh of renewable electricity per year, enough to supply more than 1.4 million Egyptian households, and to reduce carbon emissions by approximately 2 million tonnes per year.
This is the third wind farm developed by ENGIE and its partners in Egypt. It follows Ras Ghareb Wind Energy (262.5 MW) and Red Sea Wind Energy (650 MW), both delivered ahead of schedule. Together, the three wind farms will have a capacity of more than 1.8 GW.
Shokeir Wind Energy S.A.E. acknowledges the support of the Government of Egypt, the Ministry of Electricity and Renewable Energy, EETC and NREA in bringing the project to financial close.
“Financial close on Shokeir Wind Energy is the result of close cooperation between three shareholders who have now brought three wind farms in Egypt to this stage together. I thank the Government of Egypt, the Ministry of Electricity and Renewable Energy, EETC and NREA, as without their support such developments could not have happened. I also thank our lenders for their confidence in the company, and the teams of ENGIE, Aeolus and Orascom Construction for their work.”
Khaled El Degwy, Chairman of Shokeir Wind Energy
“With the financing in place, our focus is delivery. Construction is proceeding at full scale, and we are working towards commissioning of the first 300 MW in January 2028 and full commercial operation in the third quarter of 2028. We will build this wind farm with the same commitment to safety, quality and the local community that marked the Ras Ghareb Wind Energy and Red Sea Wind Energy projects.”
Mohamed Awny, Chief Executive Officer of Shokeir Wind Energy
“This financing brings together development finance institutions, export credit and commercial banks from Japan and Europe, with HSBC Bank Egypt onshore. Their participation on a non-recourse basis reflects confidence in the project, in the Power Purchase Agreement with EETC and in Egypt’s renewable energy programme. We thank each of them for their support.”
Sanae Akiyama, Chief Financial Officer of Shokeir Wind Energy